A contract was made for 125 bales of cotton to arrive on a ship named "Peerless" from Bombay. Unbeknownst to either party to the contract, there were two ships named "Peerless," both of which were sailing from Bombay. One sailed in October and the other in December. The buyer had in mind the ship sailing in October, but the seller had in mind the ship sailing in December. Each party held his belief in good faith. When the goods failed to arrive on time, the buyer sued for breach of contract.

A contract was made for 125 bales of cotton to arrive on a ship named "Peerless" from Bombay. Unbeknownst to either party to the contract, there were two ships named "Peerless," both of which were sailing from Bombay. One sailed in October and the other in December. The buyer had in mind the ship sailing in October, but the seller had in mind the ship sailing in December. Each party held his belief in good faith. When the goods failed to arrive on time, the buyer sued for breach of contract.


a. The seller is in breach and must pay damages.

b. The seller is guilty of fraud in the inducement for failing to disclose to the buyer which ship would contain the goods.

c. No contract exists due to mutual mistake of fact as to the existence or identity of the subject matter of the contract.

d. Two of the above, (a) and (b).



Answer: 

Comments

Popular posts from this blog

Fred is a concert violinist who is scheduled to perform at Carnegie Hall for the first time. He buys what he is told is a Stradivarius violin from a well-known, reputable dealer in quality violins, and he pays the going rate for a Stradivarius. He later learns the violin is an imitation, although it is such a good imitation that even the dealer thought it was authentic.

Alex wants to submit a bid on a city sewer project. He computes the cost, but mistakenly omits the cost of one item. Accordingly, he submits a bid of $430,000 to the city. The next highest bid is $675,000, and the rest of the bids are even higher. The city is happy to have such a low bid, so it accepts Alex's bid and awards him the contract for the job, even though the city engineer is of the opinion the job cannot be done for less than $650,000.